Construction work on ICT admin complex reviewed

Islamabad: Physical progress of the newly under construction building of the ICT Administration Complex at Sector G-11/4, Islamabad, was reviewed at a high-level meeting chaired by the Chief Commissioner, Islamabad, Tariq Mahmood Pirzada here on Tuesday.

The meeting was informed that 90 per cent work of the new building of ICT Administration Complex, Sector G-11/4 Islamabad has been completed and remaining 10 per cent construction work of boundary wall, landscaping and foot paths would be completed by 31 December, 2011.
The Chief Commissioner directed the Project Director, CDA to complete the remaining 10 per cent construction work of boundary wall, footpaths and landscaping, installation of walk through gates by December 26, and also ensure the provision of Water and Sui Gas connections to the newly constructed building by December 26.
The offices of the Chief Commissioner, Islamabad and Deputy Commissioner, Islamabad are likely to be shifted to the newly constructed building of ICT Administration Complex, Sector G-11/4 during the last week of December.
This meeting was attended by the Member(Engineering) CDA, Director Development/Finance, ICT, Rana Akbar Hayat, CDA Project Director of ICT Administration Complex and other officials of the administration. Online